Demonstrator · assumptions, not quotations

Cost and consequence

What a three-tier slope monitoring programme costs to build and to run, and which kinds of failure it would actually have caught. The second question matters more than the first, because a programme that claims to catch everything will be disbelieved by the first engineer who reads it.

Every unit cost here is an author assumption with a range, not a quotation. No supplier has been approached and no Nepali procurement data has been used. The purpose is to show the shape of the spend and what it would have to be worth, so that real numbers can replace these without changing the argument.

What it costs

Network

Narayanghat to Mugling held 123 in 33 km. Scale that across the network and this is the order of magnitude.

Shown in tenths of a percent. The instrumented tier is deliberately tiny and is chosen by the screening.

Unit assumptions, USD

Year one, build and run

Steady state, every year after

—

What it would catch, and what it would not

Six mechanisms, animated. The verdict on each is whether satellite screening and instrumentation would give useful warning. Two of the six would not be caught at all, and saying so is what makes the other four believable.