Concept note · November 2026

The Seasonal Energy Procurement Programme

Buying the season Nepal is short of. A technology-neutral procurement programme built on the South African framework, designed to close the dry season gap without competing with hydropower, and structured so that Nepal's own budget need not carry it.

FOR: THE RT HON PRIME MINISTER BALEN SHAH
COPY: HON MINISTER OF ENERGY, WATER RESOURCES AND IRRIGATION
COPY: ELECTRICITY REGULATORY COMMISSION · NEPAL ELECTRICITY AUTHORITY

Why this note, and why now

At one hundred days, this government was credited with putting energy at the centre of its economic strategy and with cancelling inactive licences, but assessed as stopping short of structural transformation and as having yet to secure the confidence of major international strategic investors. This note proposes one instrument that addresses both, and it has been done before: South Africa used it to move roughly 9,900 MW to 127 private projects across seven bidding rounds, financed by its own commercial banks, against a utility nobody wanted to lend to.

1,100 MW imported from India in the dry season, while 600 to 700 MW is exported in the monsoon
12,135 MW of hydropower already under power purchase agreement, against 4,120 MW built
0 MW of wind, because no tariff, no agreement and no procurement route exists for it

01
The problem is a season, not a shortage

Nepal does not lack generation capacity on paper. It lacks generation in the months its rivers run low, and it buys that shortfall from India at a price it does not control.

In the 2025/26 financial year Nepal imported 1.15 billion units for NPR 10.56 billion, an average of NPR 9.18 per unit, while exporting at an average of NPR 7.56. In the April to May 2026 window, no supplier bid at the tendered ceiling at all, and supply was subsequently restricted to sixteen hours a day. A country that exports power for half the year is paying a premium to import it for the other half.

Wind in Nepal peaks when the rivers do not. Analysis of twenty five years of reanalysis data at the Butwal grid cell indicates that roughly 60 percent of annual wind energy falls between December and May, with March and April alone carrying about 30 percent. Those are the months of lowest river flow and highest import dependence. Shape derived from NASA POWER 2001 to 2025; magnitude is unmeasured.

02
Where the resource is, and where it can be built

The two are not the same place, and the difference decides the programme's first round.

Gandaki holds the best wind and cannot receive a turbine blade. Global Wind Atlas power density at 100 metres gives Gandaki 950 W/m² over its windiest tenth against Lumbini's 534, but Gandaki's resource lies in Mustang and the upper Kali Gandaki, reached by mountain track. Lumbini's ridge above Butwal is half the resource, thirty to fifty kilometres from the Indian border, at a 400 kV node, on the only corridor that can carry a blade. Schematic, not to scale.
Lumbini ridge Candidate first round site. 534 W/m² over the best tenth, 1,045 over the best 2 percent.
New Butwal 400 kV Substation under construction. Connection point and the Gorakhpur cross-border link, rated 3,500 MW.
Bhairahawa / Nautanwa Heavy cargo gateway. Rail access extended to Nautanwa under the 2025 transit protocol amendment.
Mustang, Kali Gandaki Nepal's best wind, 950 W/m². No road capable of a 45 metre blade. Later rounds only.
Hetauda to Dhalkebar 400 kV, 134 km. Raises transfer from about 300 MW to about 2,000 MW. Energisation expected late 2026.
Tingla, New Khimti, Dhalkebar 134 km 400 kV under ADB public private partnership advisory. Rated 4,080 MW on completion.

03
The engineering is solved. The logistics are not.

Nothing proposed here requires a technical advance. The machines exist, they are built next door, and they already operate higher in the Himalaya than anything Nepal would attempt.

Since January 2024 a 100 MW wind farm of twenty five turbines has operated at 4,650 metres in Nagqu, Tibet, and a 2013 project claimed 4,900 metres. A Nepali site on the Lumbini ridge sits near 1,400 metres. Even Mustang, at 2,700 metres and above, would be well below what is already running across the border. The useful claim is therefore not that Nepal would build the world's highest wind farm. It is that the hard engineering has already been done, in the same mountain range, by a neighbour.

Two real constraints remain, and neither is exotic.

Thin air costs output, and must be priced in

Power scales directly with air density, and a manufacturer's power curve is quoted at sea level. At 1,400 metres the air is 87 percent as dense, so the same wind yields about 13 percent less energy. At Mustang it falls to around 70 percent. Any Nepali wind assessment that applies a standard power curve without this correction overstates its yield, and this note's own worked example was revised downward once the correction was applied. The answer is a larger rotor per megawatt, which is precisely how high altitude machines are built.

The binding constraint is a blade on a road

Nepal has deep experience moving hydropower transformers and turbine runners, which are heavy and compact, so the constraint is axle load and bridge capacity. A blade is light and very long, so the constraint is swept path radius on hairpin bends. The country's track record does not transfer. Every blade factory in India lies to the west or the south, 1,300 to 1,600 kilometres from the border, and the only gateway that can plausibly carry one is Bhairahawa to Butwal. That single fact decides where a first round is sited, and it is why the best resource in Gandaki is not the first round's target.

04
What the South African programme actually is

Four contracts and an office. Not a subsidy, not a fund, and not a target.

South Africa's banks did not lend against the utility's balance sheet. They lent against a government undertaking that the utility would be able to pay. That single document is what converted an unbankable offtaker into twenty year project debt, in local currency, from local banks.

The power purchase agreement sells the electricity. The implementation agreement makes the promise to pay creditworthy. The direct agreement lets lenders rescue a failing project instead of losing their money. The programme office runs the rounds and holds the institutional memory. Everything else follows from those four.

05
Instrument by instrument, and what Nepal already has

InstrumentWhat it does Nepal today
Power purchase agreement
IPP and NEA
Standardised, non-negotiable, local currency, twenty years, indexed. Non-negotiability is the point: it ends bilateral haggling and makes every project bankable on identical terms. Partly exists
NEA signs at scale, 545 projects. No wind agreement, no wind rate.
Implementation agreement
IPP and the Ministry
Government undertakes to fund the utility's payment obligations where the tariff does not cover them, backed by a guarantee. This is the document the banks lend against. Does not exist
The single largest gap, and the reason the programme cannot simply be announced.
Direct agreement
IPP, NEA, Ministry, lenders
Gives lenders step-in rights if the project company fails. Note the limit: it does not cover developer default, it gives lenders time to cure before termination. No template
Consortium lending already works. Budhigandaki drew NPR 52.5bn from ten institutions.
Procurement office
Agent of the Ministry
Runs the rounds, evaluates bids, holds the programme's memory and its standard documents. Does not exist
The Department of Electricity Development licenses; it does not procure competitively.
Request for proposals
Programme to market
Carries the development obligations: local content, community ownership, jobs. Scored at bid, then contractually binding. Not for wind
Shape to Nepali priorities: provincial benefit sharing, community equity, local manufacture.
Tariff determination
The regulator
In South Africa the price is bid. In Nepal the Commission determines it, which is faster for a first round where no price discovery exists. Capability exists
The Commission already sets seasonal rates for reservoir hydropower. Only extension to wind is needed.

06
Adapting the hydropower framework rather than building a new one

Almost everything this programme needs already exists in Nepal, written for hydropower. The work is adaptation, not invention, and that is what makes it fast.

What exists for hydropower What has to change for seasonal generation Effort
Seasonal tariff determination
ERC, February 2026
The winter and rainy season split already exists for reservoir projects at NPR 14.80 and 8.45. Extend the same seasonal structure to other technologies, with the dry season rate benchmarked to the cost of energy displaced rather than to the solar rate. Extend an existing determination
Standard NEA power purchase agreement
545 projects signed
Replace hydrological provisions with resource provisions: no deemed generation on river flow, an availability rather than output obligation, curtailment rules for the monsoon surplus, and metering at the connection point. Amend clauses, keep the spine
DoED survey and generation licensing
established process
A survey licence for hydropower protects a river reach. For wind or solar it must protect a land area and a measurement campaign instead. Same instrument, different object. Redefine the licensed object
Consortium project finance
NPR 52.5bn across ten institutions
Nothing structural. Lenders need a resource report in place of a hydrology report, and a precedent transaction. The syndication machinery already works. Already capable
Mandatory public offering and NEPSE listing
hydropower listings dominate the exchange
Nothing, once a power purchase agreement exists. A signed agreement is the precondition for a public issue, which is one more reason the tariff determination comes first. Applies unchanged
Government payment support
no general instrument
This is the one thing with no hydropower precedent to adapt. It has to be created. Build from new

Five of the six are adaptations of instruments the state already operates competently. That is the argument for speed: a seasonal procurement programme is not a new system bolted onto the sector, it is the existing hydropower system taught to buy a second kind of electricity.

07
Wind does not need a new rate. It needs the right existing one.

Nepal already operates four published rate cards. Three of them are seasonal, and two use exactly the same seasonal ratio. Wind fits this structure without any new principle being invented.

Nepal pays NPR 9.18 per unit for the energy it imports in the dry season, and that is the line every card should be read against. Two cards are cheaper than importing and two are dearer. The difficulty is that the two cheap ones do not finance a project: at the solar rate a worked example reaches 0.28 times debt service cover, and at the run-of-river rate 0.45 times. The reservoir card carries the project and costs the country roughly NPR 189 million a year more than importing. That tension, not the seasonal principle, is the real decision. Note also that each card pays wind more than it pays hydropower, because about 60 percent of wind output lands in the dry season against roughly 28 percent for run-of-river.

Nepal's seasonal premium is already a settled number

Run-of-river pays NPR 8.40 in the dry season against 4.80 in the wet, a ratio of 1.75. Reservoir hydropower pays 14.80 against 8.45, a ratio of 1.75. The same figure appears in two determinations made years apart for different technologies. The question for wind is therefore not what the seasonal ratio should be. It is which card applies.

And the answer sits between two existing cards

Run-of-river hydropower is non-dispatchable and delivers in the wrong season, and is paid 8.40 in the dry months. Reservoir hydropower is dispatchable and delivers in the right season, and is paid 14.80. Wind is non-dispatchable but delivers in the right season, so it sits honestly between the two. Peaking run-of-river, at 10.55 and 8.40, is the closest existing analogue and would be the defensible starting point. Paired with the battery storage Nepal is already procuring, the case for the reservoir card becomes arguable rather than opportunistic.

No new law is required, and there is a recent precedent

The Electricity Regulatory Commission, established under its 2017 Act, holds a general power to fix the purchase price of electricity. That power is not written per technology, so extending it to a new one is a determination rather than an amendment. The Electricity Bill 2080 remains before Parliament, but nothing proposed here waits on it.

The Commission also already has a published method. The Electricity Regulatory Commission Rules, 2018 empower it to set standards for power purchase and sale rates, and define the basis explicitly: loan interest, depreciation, return on investment, operation and maintenance cost, tax, and the loan to equity ratio. The Rules also contemplate a two part tariff, with a capacity charge covering debt and an energy charge covering equity return, tax and operating cost. A draft amendment sets the return on equity for generation licensees at 16 percent, with an additional 1 percent in defined cases, and that draft should be confirmed against the final text.

This is a cost-plus methodology capped at a regulated return. It is exactly how a rate for a new technology would be built, and it is the clearest possible reason that measurement precedes the rate: the Commission cannot apply a cost-based method to a resource whose output nobody has measured.

The Commission has already scheduled this work

Its own published Five-year Roadmap for 2024 to 2029 lists "Determination of Power Purchase Rate and Approval of Power Purchase Agreements" as a priority, and sets out a planned directive specifying the basis and standards for generation purchase rates. That directive has not yet been issued.

So a submission on seasonal generation does not arrive uninvited. It arrives as input to a workstream the regulator has already committed to, before the directive is written rather than after. That is a materially easier thing to ask for, and the window closes when the directive issues.

Solar went through this door two years ago. Three administrative steps.

Solar had no window and no rate either. It now has both, and the route was entirely administrative:

One. The NEA board resolved to open a purchase window, with a capacity cap. Solar's was framed as a share of the energy mix, with the contribution limited to about 10 percent of total contracted capacity. A comparable cap for seasonal generation would reassure the hydropower sector rather than alarm it.

Two. NEA proposed a rate, developed through a task force, and submitted it to the Commission.

Three. The Commission approved it, and NEA then signed at or below that base rate through competitive bidding.

The result is visible in the numbers. In FY2025/26 NEA signed 54 power purchase agreements, of which 49 were solar and five were hydropower, with solar taking roughly 675 MW against under 29 MW for hydropower. A technology with no route at all became the majority of new contracting inside two years, without legislation. That, rather than South Africa, is the nearest precedent for what is being asked.

08
The carbon position, stated carefully

Nepal's grid is already roughly ninety five percent renewable, so its grid emission factor is near zero. Wind that displaces Nepali hydropower has almost no carbon value, and any claim built on the domestic emission factor will not survive international diligence. It should not be made.

The carbon sits entirely in what the dry season output actually displaces, which is imported power from a coal-heavy Indian grid, in the months Nepal cannot supply itself. That is a genuine and substantial decarbonisation claim, and it is a cross-border one requiring corresponding adjustments under Article 6 of the Paris Agreement. Nepal has the institutional experience: in January 2026 it signed an emission reductions purchase agreement with the LEAF Coalition for up to four million tonnes from Gandaki, Bagmati and Lumbini, reported as the first globally to offer correspondingly adjusted credits to private buyers. That was forest carbon. The energy equivalent has not been attempted by anyone.

Indicative only. The relative height is the argument, not a calculated emission factor. Quantification requires both grids' factors, an hourly dispatch assumption and an Article 6 pathway.

09
What the first round costs the country

At the tariff that finances it, a first round project costs Nepal more than importing the same energy. That belongs in front of a decision maker before a signature, not after one.

Taking the 21 MW worked example: it would produce about 64 GWh a year, roughly 39 GWh of it in the dry season, for a capital cost of about USD 26 million and an operating cost of about USD 39 million across twenty five years. Over that life it delivers roughly 930 GWh of dry season energy. Nepal currently buys that same energy from India for about NPR 8.54 billion, or USD 61 million, at last year's average of NPR 9.18 per unit.

Only the tariff that nobody will build at is cheaper than importing. At NPR 8.50 the project undercuts imports by NPR 633 million but reaches a debt service cover of 0.72 times, so it does not get financed. At the NPR 14.54 it needs at a 35 percent capacity factor, it costs Nepal about NPR 5.0 billion, or USD 35 million, more than imports over twenty five years. That is more than the project costs to build. Correcting for air density at 1,400 metres pushes the break-even higher still, to roughly NPR 17 per kWh, above the reservoir hydropower winter rate, which is why a measurement campaign comes before any commitment.

So the question is not what it saves. It is what the premium buys.

Four things, and a government should weigh them explicitly rather than be told the project pays for itself.

Supply that exists In April to May 2026 no supplier bid at the tendered ceiling and India cut supply to sixteen hours a day. You cannot import electricity nobody will sell, and no price appears in a table for energy that is unavailable.
USD 61m of foreign exchange retained Over the asset's life, in a utility whose profit fell sharply on foreign exchange losses. That money leaves the country today. Under domestic generation it circulates in rupees.
651,000 tonnes of CO2 About 27,000 tonnes a year displaced from a coal-heavy grid. At USD 20 a tonne that is USD 13 million, roughly a third of the premium. It depends entirely on the Article 6 claim above.
Price discovery South African tariffs fell sharply once bidders had data to price against. The first round is not a least cost purchase. It is the cost of learning what Nepali wind actually delivers.

Which is precisely why the first round should be small

A premium of USD 35 million spread across twenty five years is about USD 1.4 million a year. That is affordable as a national learning cost, and it is the strongest argument for a first round of 50 to 100 MW rather than a headline number. The same premium applied to 500 MW would not be defensible, and any proposal for a large first round should be tested against this arithmetic before it receives support.

The premium also shrinks on its own. Every increase in the import price, and the two governments agreed a 1.5 percent rise in March 2026, narrows the gap. So does a capacity factor above the 35 percent assumed here: at 41 percent the break-even falls to NPR 11.83 and the premium halves. Both are reasons to measure before committing, not reasons to assume.

10
Who pays, at every stage

This is the section to read if the question is whether the country can afford it. On the structure proposed here, Nepal's own budget carries none of it.

Four stages, four different sources, and the national budget appears in none of them. Grant money funds the measurement and the legal work because those produce a public good: the first bankable wind record in Nepal and a set of standard documents, neither of which expires. Private capital funds construction because by then there is something to lend against. Government contributes documents, not money.

And the premium is cheaper bought once than rented for 25 years

The gap between what a first round project costs and what the energy is worth can be paid two ways. Through the tariff, it is paid for twenty five years at a lender's cost of capital. Bought down once as a capital grant, it carries no interest at all. The same gap costs several times more if it is rented through the tariff than if it is purchased up front, which is the single strongest argument for routing concessional money into capital grants rather than into tariff support.

Nepal already operates the instrument. The Central Renewable Energy Fund, managed by the Alternative Energy Promotion Centre, provides viability gap funding to bring private capital into renewables, and the Centre is the country's first accredited Direct Access Entity to the Green Climate Fund, meaning it can seek and channel that money directly rather than through an intermediary.

11
What only government can do

Two documents. Everything else in this programme can be delegated, contracted, donor-funded or bought in.

A tariff determination and a payment undertaking are sovereign acts. No development bank, consultant or developer can perform them, and no amount of concessional capital substitutes for them. They are also the two cheapest items in the entire programme, costing drafting time rather than money. Everything in the right column can be paid for by somebody else.

Which makes the ask unusually small

The government is not being asked to fund a programme. It is being asked to issue a tariff determination it has already made for another technology, and to sign a payment undertaking of the kind that South Africa used to attract roughly 9,900 MW of private investment. Those two acts unlock grant funding for everything upstream of them and private capital for everything downstream.

If both are refused, nothing else in this note matters and no amount of donor interest will produce a project. That is worth stating plainly, because it is the whole decision.

Administer before you bid

South Africa bid competitively from the first round because solar and wind costs were internationally established. Nepal has no wind operating record, no measured yield and no delivered cost, so a competitive first round would attract either no bidders or unserious ones. The first round should use an administered tariff. Competitive bidding follows once cost and yield precedent exist, and South Africa's own experience supports this: its tariffs fell sharply only once bidders had data to price against.

12
How it would be built

  1. Establish the instruments Months 0 to 12 · technical assistance, not capital

    The Commission determines a wind tariff with seasonal differentiation. The Ministry drafts the implementation agreement and the government support mechanism. NEA adapts its standard power purchase agreement. A procurement unit is designated, either new or inside the public private partnership capability the Asian Development Bank is already building with NEA.

  2. Administered first round Months 12 to 24 · 50 to 100 MW

    Three to five projects at an administered seasonal tariff, sited where construction is actually possible rather than where the wind is best. The purpose is precedent, not volume.

  3. Competitive bid windows Months 24 to 48

    With cost, yield and delivery precedent established, move to competitive bidding on the standard documents. This is the point at which tariffs begin to fall.

  4. Programme at scale Month 48 onward

    Regular rounds, standard documents, a known lender group. Wind becomes ordinary procurement rather than a first of a kind, and the dry season import bill begins to fall.

13
What this is not

It is not a move away from hydropower

NEA holds power purchase agreements for 12,135 MW of hydropower and the independent producers are hydropower developers. They are the constituency this programme needs, and nothing is gained by positioning wind against them. Wind does not substitute for hydropower. It substitutes for imports. It generates in the months their assets cannot, it earns the dry season rate their reservoir projects already earn, and it strengthens the sector's case that Nepal can supply itself year round.

It is not a request for capital

Phase one is a legal, regulatory and institutional exercise. It is the kind of work development banks fund as technical assistance, and both the Asian Development Bank and the World Bank are already positioned: ADB holds Nepal's first public private partnership transaction advisory mandates with NEA, covering a 400 kV line and multisite battery storage. A wind procurement framework is an adjacent, smaller and faster mandate than either.

14
A worked example already exists

Project Vayu is a 21 MW dry season wind proposal on the Lumbini ridge above Butwal, at the New Butwal 400 kV node. Its analysis is complete to pre-feasibility: resource shape from twenty five years of reanalysis, magnitude from the Global Wind Atlas, a logistics assessment from the Indian manufacturing base to site, a financial model and a public scenario tool.

Its own documentation states plainly that it does not finance at today's tariffs and that its yield has never been measured. It is offered here not as a project seeking approval, but as a worked example of exactly what this programme would have to make financeable, and as a candidate for the administered first round. A programme designed around one real project survives contact with reality better than one designed in the abstract.